Citizen Soundkeepers
Stormwater Program
Permit Review
Legal Action
 
 
 
 
Legal Action

Protecting Puget Sound water quality from manure generated by factory farms

Did you know that the average 1400 pound dairy cow produces 120 pounds of “wet raw manure” per day? Did you know that a large “concentrated animal-feeding operation” (CAFO) with 700 or more mature dairy cows produces approximately 84,000 pounds of manure per day? If you do the math, the results are staggering! With 700 large and medium CAFOs in Washington State, there are 58.8 million pounds of manure produced everyday!

In January 2005 the Washington State Department of Ecology (Ecology) proposed that certain animal feeding operations be required to protect water quality under a new general permit. According to Ecology, “the permit would require CAFOs - such as cattle feedlots, dairies, and poultry or pig producers - to manage manure to avoid polluting rivers, lakes and underground aquifers.”

To be a large CAFO, the lot must have animals that will be stabled or confined and fed, or maintained for a total of 45 days per year and there are no crops or vegetation able to be sustained on the lot where the animals are confined. In addition, the number of animals to be stabled or confined is defined. For example, a large CAFO must have 700 mature dairy cows, 1,000 veal calves 1,000 cattle, 2,500 swine (each weighing 55 pounds or more), 10,000 swine (less that 55 pounds), 500 horses, 10,000 sheep or lambs, 55,000 turkeys, 30,000 laying hens or broilers, or 125,000 chickens.

The draft permit prohibits the discharge of manure, litter, or process wastewater into waters of the state, e x cept when the design standard of the production area is e x ceeded in a 25 year, 24 hour storm. The permit also requires the creation of a Nutrient Management Plan outline how the CAFO will use best management practices to keep waste out of state waters.

The Puget Soundkeeper Alliance reviewed and commented on the draft permit and identified a number water quality related issues. The release of the final permit has been delayed as a result of an appeal by the Waterkeeper Alliance, of which the Puget Soundkeeper Alliance is a member. The Waterkeeper Alliance and others successfully challenged EPA regulations providing guidance on how CAFO's should be regulated to protect water quality. Ecology now has to revise the draft permit based on the results of the appeal.

Meanwhile, the Washington State Department of Agriculture proposed a bill during the 2005 Legislative Session that would move the protection of water quality from agricultural sources from the Department of Ecology to Agriculture. The Puget Soundkeeper Alliance provided testimony at a number of hearing and committee meetings to insure that if the program was re-delegated to Agriculture, that it be the same program as Ecology's in order to maintain the same approach to regulating pollution. SSB 5602 as it was signed into law requires only that Ecology and Agriculture come back to the legislature with recommended statutory changes prior to applying to the EPA for delegated authority to administer the CAFO portion of the National Pollutant Discharge and Elimination System permit program under the federal Clean Water Act. It is possible that these proposed changes will come before the Legislature in 2006.

For more information:

Department of Ecology http://www.ecy.wa.gov/programs/wq/permits/cafo/index.html

Waterkeeper Alliance
http://www.waterkeeper.org/

-----------------

Utilizing the authority of the citizen suit provision of the Clean Water Act, Puget Soundkeeper Alliance has confronted several significant violators of the Act's provisions.

McNeil Island Corrections Center sewage treatment plant plagued by 350 pollution violations

In January 2005, PSA sent McNeil Island Corrections Center a 60 day notice of intent to file suit under the Clean Water Act for over 350 violations of effluent limits for fecal coliform, pH, biological o x ygen demand, suspended solids and flow between 2002 and 2004. The sewage treatment plant which was built in 1971, then upgraded in 1991. In 2003, the plant was converted to a conventional activated sludge treatment processes in order to treat increases in flow and pollution resulting from projected increases in inmate populations. A water quality testing lab was added to the facility and staff training completed. As a result of this new information and no ongoing effluent violations, PSA will continue monitoring the Center's pollution discharges. The Puget Soundkeeper Alliance (PSA) was represented by Rick Poulin of Smith & Lowney.

 

Sand and Gravel Permit appealed

On February 4, 2005 PSA appealed the newly updated Sand and Gravel General permit which regulates the discharge of stormwater, process water and mine dewatering water from 928 sand and gravel operations, rock quarries, and similar mining operations, including stockpiles of mined materials. The permit also covers concrete batch and hot mi x asphalt operations.

 

The pollutants associated with sand and gravel operations include pH, turbidity, TSS (Total Suspended Solids), temperature, oil and TDS (Total Dissolved Solids), which are regulated by Washington State because of the harmful impact on aquatic life when discharged to creeks, streams, rivers and Puget Sound .

 

PSA appealed the permit because it failed to comply with the Clean Water Act, the Washington State Pollution Control law, and Washington State Department of Ecology regulations. The Washington Aggregates and Concrete Association also appealed the permit. PSA is currently in settlement negotiations and is represented by Richard Smith of Smith & Lowney in Seattle .

 

Snohomish County settlement negotiations continue

In September 2004 PSA sued Snohomish County , under the Clean Water Act, for failing to implement the current Stormwater Management Manual (2005) as required by its 1995 Municipal Permit. The goal of this lawsuit is to protect water quality by enforcing the implementation of the state of the art stormwater management techniques described in the Manual. PSA is currently in settlement negotiations with the County. PSA is represented by Richard Smith of Smith & Lowney.

 

Stormwater regulation update

The Department of Ecology has released, since the first of the year, 5 stormwater permits for review and comment including the Boatyard General Permit (107 permit holders), Consolidated Animal Feeding Operations Permit (700 permit holders), Construction Stormwater General Permit (1,800-2300 permit holders), Municipal Stormwater Phase I permit (Seattle, Tacoma, King, Snohomish, Pierce and Clark Counties) and Municipal Stormwater Phase II permit (85 permit holders). PSA is currently reviewing the permits for compliance with the Clean Water Act. Stormwater pollution is the largest source of impaired waters in Puget Sound .

-----------------

Blake Island State Park Beach violates pollution permit 320 times

The Washington State Department of Health has closed much of the eastern and northern shores of Blake Island to shellfish harvesting due to pollution.

Since 1998 the Blake Island State Park Sewage Treatment Plant has violated its Department of Ecology issued pollution discharge permit 320 times by discharging more fecal coliform, BOD (biological oxygen demand), suspended solids and chlorine than allowed by the permit to protect water quality. The Plant, which is managed by Washington State Parks, has also failed to submit discharge monitoring reports in a timely manner, failed to submit discharge monitoring reports for certain months, and failing to test discharge parameters as required.

The 475 acre Blake Island State Park is well known for its 5 miles of beaches and scenic view of Mt. Rainier, the Olympic Mountains and Seattle. The Park, which receives over 200,000 visitors a year, is responsible for collecting and treating the sewage created on the island from use of its restrooms, staff residences, marina pump-out and the Tillicum Village concession. The sewage treatment pipe discharges its effluent into Puget Sound through a 600 foot pipe that discharges in 30 feet of water off the beach on the eastern shore with a mixing zone of 230 feet. A mixing zone is permitted because the plant can not meet water quality standards at the end of the pipe.

PSA is currently in settlement negotiations with the attorney general's office, which represents Washington State Parks. PSA is represented by Rick Poulin of Smith & Lowney, PLLC.

Pollution Control Hearings Board Stormwater Decision Appealed

Good stormwater regulations seem to take a long time! PSA and its co-appellants are now in the third year of an administrative appeals process that is determining the extent to which industrial stormwater dischargers must protect water quality. In June the Pollution Control Hearings Board (PCHB) ruled favorably on three of our four major issues. PCHB ruled that the endless compliance schedule, which would have delayed compliance with water quality standards indefinitely, was ruled invalid. PCHB also ruled that the standard mixing zone provisions in the permit, which would allow any discharger to get a mixing zone if it can't meet water quality standards at the end of its pipe, without any Ecology determination, was invalid. Finally, PCHB remanded sections of the permit, which allowed Ecology to modify the permit without public participation. The ruling on our fourth issue, monitoring, was issued in August PCHB remanded three issues related to stormwater sampling to Ecology. In early September the Association of Washington Businesses, PSA and its co-appellants and Ecology appealed the PCHB orders. PSA is currently in settlement negotiations.

Can the state legislature pass laws that violate the Clean Water Act?

PSA joined a statewide coalition of environmental groups to urge the Washington State Supreme Court to review and reject the SB 5787, the so-called "Dirty Fill Bill" that was pushed by the Port of Seattle and passed in special session in May 2003. The bill eliminates an important protection for stormwater running off Sea-Tack Airport that was imposed by the Governor appointed Pollution Control Hearings Board. The groups are filing the amicus brief because the "Dirty Fill Bill" is an impermissible end run around the courts, violates the separation of powers doctrine and results in a policy that is contrary to the federal Clean Water Act. If this bill is allowed to stand, it would set a statewide precedent that would encourage the state legislature to create laws that violate the Clean Water Act and other federal pollution control laws. PSA and the coalition are represented by William Rodgers.

Three Clean Water Act Cases settled! $186,000 in penalty money raised to support clean water!

Todd Shipyard was notified of PSA's intent to sue under the Clean Water Act in February 2002 for violations of stormwater effluent limits including turbidity, suspended solids and oil and grease. We filed the compliant in April 2002 and finalized a consent decree in September 2003. The consent decree requires Todd Shipyard to complete the construction of and have operational its Contaminated Industrial Stormwater Collection and Treatment System no later than January 1, 2004. Todd will be collecting, treating and discharge to the sanitary sewer, stormwater that is falling on 14 acres of the industrial portion of its site. Todd will also pay $25,000 in mitigation to RE Sources for Sustainable Communities to conduct a stormwater discharge research project aimed at identifying and permitting, unpermitted stormwater dischargers. PSA was represented by Richard Smith of Smith & Lowney.

PSA signed a Settlement and Release Agreement with Fisherman's Bay Sewer District on July 15, 2003. By November 30, 2003 the District will complete the construction and upgrade projects for its lagoon treatment system and achieve full compliance with its NPDES permit. Two thousand dollars was earmarked for facility management and permit compliance training for the District's operator and $18,000 will be used to convert one of the wastewater lagoons to a constructed wetland for tertiary wastewater treatment. We were represented by Paul Kampmeier of Smith & Lowney

PSA signed a consent decree with Oly-Rose LLC, which manages the sewage treatment plant at Rosario Resort on Orcas Island. At issue were violations of their effluent limits for fecal coliform, chlorine, and BOD. The consent decree requires Oly-Rose to pay $90,000 in three installments to the Islands Oil Spill Association and Friends of the San Juans. It addition, Oly-Rose will develop and implement a pollution education program for Rosario Resort Employees and boaters using the Rosario Marina at a cost of $8,000. Oly-Rose recently violated its permit by accidentally discharging 28,000 gallons of untreated, raw sewage into East Sound. We were represented by Paul Kampmeier of Smith & Lowney.

PSA also signed a consent decree with JA Jack & Sons, a limestone processor on the Duwamish River in Seattle for violations of turbidity limits in their stormwater discharges. The Duwamish River Clean Up Coalition will receive $35,000 to implement a Duwamish Restoration and Water Quality Project.

Consent decree monitoring

PSA is monitoring consent decree compliance with the, City of Bremerton, City of Ferndale, Fisherman's Bay Sewer District, City of North Bend Sewage Treatment Plant, City of Snohomish Sewage Treatment Plant, JA Jack & Sons, Oly-Rose LLC, Spadoni Brothers, Todd Shipyard, and Warm Beach Christian Camp and Conference Center.


Stormwater discharges from 95 Urban Cities and Counties are on the path to regulation

The Westside Municipal Stormwater Advisory Group, of which PSA is a member, was formed this past summer in acknowledgement of the Washington State Legislature's interest in municipal stormwater discharges during the 2003 Legislative Session. The Advisory Group, which consists of city and county, business, environmental, shellfish, agriculture and port representatives, is working in a facilitated process to frame significant policy issues related to the development of a permit to regulate stormwater discharges from municipal separate stormwater systems. The group met every two weeks between September and December to provide input on a wide range of water quality issues to the Department of Ecology, which will report to the Governor and Legislature in December 2003. The focus of the debate is on how many urban areas much do to protect water quality from polluted stormwater.
-------------

Legal Accomplishment History

The following is a summary of the results of the Alliance's Clean Water Act enforcement (dates in parentheses indicate PSA's first legal action).

Sewage Treatment Plants

Fisherman Bay Sewer District (2003)

I. Background

Fisherman Bay Sewer District operates a municipal wastewater treatment plant on Lopez Island in the San Juans. This plant was responsible for ongoing violations of effluent limitations in the Sewer District's NPDES permit, including biochemical oxygen demand, fecal coliform, total suspended solids, and pH. The Sewer District also failed to report violations and properly retain records related to its discharges.

II. Legal Action

Based on information from the Washington State Department of Ecology (DOE), Puget Soundkeeper Alliance (PSA) sent the Sewer District a Notice of Intent to File Suit in April 2003, including in the notice all of the above violations of the Sewer District's NPDES permit. PSA and the Sewer District entered in to a Settlement Agreement in July 2003.

III. Results

By November 2003, Fisherman Bay Sewer District must complete construction of several upgrade projects at its treatment facility, including construction of an anaerobic cell, installation of baffles in its secondary treatment lagoon, reconfiguring the piping and aeration system in the secondary lagoon, and installation of a bypass pipe between the influent source and the secondary lagoon. The Sewer District must also install and maintain an additional liner strip over the secondary lagoon. The Sewer District must reach full compliance with its NPDES permit by November 2003.
In addition, the Sewer District will spend an additional $2,000 on training for its facility operator to help prevent future violations, and will complete the design and construction of a wetlands for tertiary treatment of wastewater by the end of 2005, at a cost of approximately $18,000. If the wetlands project is not completed, the Sewer District will instead make a payment of $16,000 to ReSources for Sustainable Communities, funding a Lopez Island Watershed Pledge, which will assist residents in controlling non-point pollution.


Oly Rose, LLC (2002)

I. Background

Oly Rose operates a wastewater treatment facility at Rosario Resort on Orcas Island in the San Juans. This facility violated its NPDES discharge limits for fecal coliform, chlorine, biochemical oxygen demand, and total suspended solids over 100 times from 1998 through 2001. Oly Rose also failed to properly maintain the treatment facilities at Rosario Resort, evidenced by disintegrating lagoon liners, missing chlorine vault lids, and corrosion of valves and pumps. The facility was also inadequately staffed.

II. Legal Action

Based on the numerous violations of Oly Rose's NPDES permit, Puget Soundkeeper Alliance (PSA) sent a Notice of Intent to File Suit to Oly Rose in February 2002, and filed suit in federal court in April 2002. After months of negotiations, the two parties agreed to a consent decree, still pending in court as of July 2003.

III. Results

The consent decree provides for Oly Rose to take a variety of actions to address its past violations, and to prevent future violations of its NPDES permit. Oly Rose will, over the course of two years, pay $45,000 each to the Islands' Oil Spill Association (IOSA) and Friends of the San Juans. The IOSA project will strengthen spill response and prevention resources in the San Juans, and the Friends of the San Juans will implement the San Juan County Marine Refuse Project to remove harmful debris from local beaches and waters of the San Juan Islands.
Oly Rose will also implement a pollution education and prevention program for Rosario Resort employees and boaters using Rosario Marina, and will provide conference facilities for one three-day environmental conference.
In order to prevent future illegal discharges, Oly Rose will implement numerous facility improvements. These improvements will include upgrades to the chlorination system, as well as upgrades to the various lift stations at the Rosario facility.


City of Snohomish (2002)

I. Background

The City of Snohomish operates its municipal wastewater treatment under an NPDES permit issued by the Washington State Department of Ecology (DOE). The City's sewer system is designed to allow for combined sewer overflows (CSOs). Information from the City's interactions with DOE demonstrated that the City had violated its NPDES permit due to discharges of ammonia, copper, chlorine, pH, and fecal coliform in to the Snohomish River. The City was also discharging untreated sewer effluent through unpermitted CSOs and releasing unauthorized discharges of effluent through its permitted CSOs.

II. Legal Action

Based on the information from the City's interactions with DOE, Puget Soundkeeper Alliance (PSA) filed a Notice of Intent to File Suit against the City of Snohomish in February 2002, and filed suit in federal court in April 2002. After long negotiations, PSA and the City reached a settlement, and entered into a binding consent decree in May 2003.

III. Results

The consent decree orders the City of Snohomish to reach full compliance with its NPDES permit by June 2008. In the meantime, the City must study alternatives for reducing its ammonia and chlorine discharges, complying with the effluent limits contained in its permit, and reducing the number of combined sewer overflows from its system. The City must prepare a plan incorporating these alternatives. The City must also install backup generators at its pump stations to reduce discharges during power outages.
The City will create a stormwater pollution prevention education project to aid businesses in reducing or eliminating stormwater discharges. The City will also initiate a storm drain stenciling program. In addition, the City has funded mitigation projects through the Sustainable Fisheries Foundation and the Stilly-Snohomish Fisheries Enhancement Task Force.
The City must provide quarterly reports to PSA detailing the progress and compliance with the requirements of the consent decree.


City of North Bend (2002)

I. Background

The City of North Bend operates a wastewater treatment plant that discharges in to the South Fork Snoqualmie River. A review of Washington State Department of Ecology (DOE) records revealed that the City discharged higher levels of copper, mercury, silver, zinc, and ammonia than were allowed under the permit. The City also failed to perform daily tests for chlorine as required by DOE.

II. Legal Action

In February 2002, Puget Soundkeeper Alliance (PSA) filed a Notice of Intent to File Suit, alleging that the City violated its NPDES permit requirements. The Notice identified the heavy metals discharges, testing failures, and reporting failures.

After PSA filed suit in federal court, PSA and the City reached an agreement and entered in to a binding consent decree in April 2003.

III. Results

The consent decree requires the City of North Bend to undertake four projects to help mitigate the damage caused by its wastewater discharges and prevent future damage to the South Fork Snoqualmie River. The City must:
(1) Implement a Groundwater Pollution Reduction Campaign to educate property owners using septic systems. The Campaign will last for approximately two years, and will operate at a cost of $3,000;
(2) Undertake a wetland restoration project at a cost of $7,500;
(3) Conduct a Storm Drain Stenciling Program to stencil warning labels on storm drains within its city limits. The stenciling will be completed by January 2004; and
(4) Work with the PSA to develop an enhanced water quality standards ordinance designed to reduce discharges of heavy metals to and from the wastewater treatment plant.
The City must also come in to compliance with the standards of its NPDES permit. Any future violations will result in payments by the City to the Washington Toxics Coalition.


Town of La Conner (2000)

I. Background

The town of La Conner operates a sewage treatment plant that was originally constructed in the early 1970's. The treatment plant receives influent from both the town of La Conner and the Swinomish Indian Tribal Community Village (the Tribe). The treatment plant operates under a NPDES permit that contains effluent limits for the discharge of various pollutants. From a review of Discharge Monitoring Reports submitted to the Washington State Department of Ecology (DOE), Puget Soundkeeper Alliance (PSA) identified numerous violations of discharge limits and reporting requirements included in La Conner's permit.

II. Legal Action

PSA filed a Notice of Intent to File Suit in April 2000. In this Notice, PSA specified violations of effluent limits for Biological Oxygen Demand (BOD), Fecal Coliform (FC), Total Suspended Solids (TSS), pH, and flow. For example, in 1998 and 1999 La Conner violated the TSS monthly average discharge limit for nine months during the period. In addition, PSA specified violations of the reporting requirements included in the permit, beginning in 1995 and continuing to the present. For instance, La Conner is required to monitor for Dissolved Oxygen (DO) and temperature five times a week, and then submit the results to the DOE every week. La Conner's reporting contained significant gaps, including several instances where no reports were submitted for an entire month or longer. For example, La Conner submitted no reports for DO and temperature for November and December 1999. La Conner provided no explanation for these reporting deficiencies.

III. Results

In June 2000, PSA and La Conner entered into a binding settlement agreement. The agreement recognized La Conner's difficulties with the Tribe's influent, plant upgrades La Conner had undertaken, and the expected reissuance of the permit. The agreement required La Conner to make a good faith effort to comply with the existing permit and submit a written compliance report to PSA one year after the issuance of a new permit. In addition, the agreement required La Conner to conduct a seminar on water quality issues.


City of Ferndale (1998)

I. Background

The City of Ferndale operates under a NPDES permit for the discharge of treated wastewater from its sewage treatment plant into the Nooksack River. In 1996, the Washington Department of Ecology (DOE) modified Ferndale's permit to include limits on copper and lead discharges based on water quality standards. Water quality standards were determined by an analysis of the Nooksack River to quantify background concentrations of copper and lead. In 1998 Ferndale proposed a modification of its permitted copper and lead discharge limits alleging a technical mistake in the analysis. DOE partially accepted Ferndale's proposal and relaxed the copper and lead limits. For example, lead limits were increased ten fold and copper limits were increased significantly. DOE recommended that Ferndale, in order to comply with even the relaxed limits, should work diligently with industrial users and other potential contributors to reduce the sources of copper and lead pollution.

II. Legal Action

Puget Soundkeeper Alliance (PSA) had been participating in public comment regarding Ferndale's permit since 1995. In 1998 PSA challenged the permit modification before the Washington State Pollution Control Hearings Board (PCHB), arguing that the permit modification violated the "anti-backsliding" provisions of the Clean Water Act. In addition, in May 1999, PSA formally filed suit against Ferndale alleging continued violation of copper and lead effluent limits under the modified permit. For example, PSA identified three months when the average concentration of lead discharge exceeded permit limits by a factor of five, notwithstanding the increased limits. Subsequently, PSA and Ferndale entered binding negotiations in an attempt to address the copper and lead discharges.

III. Results

In September 2000, Ferndale and PSA entered in to a binding consent decree. Under the negotiated agreement, Ferndale undertook several obligations. The city contributed $5,500 to ReSources' Marine Waters Education Program and made efforts to include children from the Ferndale School district among the participants. A storm water detention facility was constructed in 2002. Ferndale also conducted a two-day pollution prevention training seminar for Ferndale city employees and interested citizens.


City of Bremerton (1992)

I. Background

In heavy rain events, the City of Bremerton's sewer system combines surface water runoff with untreated sewage water and then discharges directly into Puget Sound. These events are termed Combined Sewer Overflows (CSOs) and occur through several designed outfalls into Sinclair Inlet, Dyes Inlet, and Port Washington Narrows. Because these outfalls are a point source for the discharge of wastewater, they are subject to NPDES permitting requirements.

The frequency and volume of CSO events resulted in significant impacts on the receiving water quality. For example, shellfish beds in the area were closed due to fecal coliform contamination. The Washington State Department of Health identified Bremerton's CSO events as the primary cause of the closure.

II. Legal Action

In August 1992, Puget Soundkeeper Alliance (PSA) filed a Notice of Intent to File Suit alleging that Bremerton's CSO discharges were violating NPDES permit requirements. In the face of uncontroverted evidence that its CSO discharges exceeded lawful discharge limits, Bremerton entered into a binding consent decree with PSA. The consent decree included several obligations on the part of Bremerton that were necessary to address the CSO problem.

First, monitoring requirements were included to measure CSOs, which had only been estimated prior to the consent decree. Bremerton agreed to install state of the art monitoring equipment on each outfall by December 31, 1993, that would record the volume and frequency for each CSO event. After actual CSO volume was determined, Bremerton agreed not to further exceed this baseline data. In addition, Bremerton would analyze water samples from each outfall for the presence of a list of contaminants of concern. This CSO volume and water sample data would then be forwarded to the PSA and Department of Ecology.

Second, Bremerton agreed to a specified schedule for the completion of a CSO reduction plan. This plan called for upgrades to the sewer system to be completed by 2011, and would result in a 90% reduction of CSO discharges. The consent decree imposed a duty on the part of Bremerton to diligently seek all state and federal funding for the completion of the CSO reduction plan. Under the consent decree, if Bremerton did not complete any of the sewer upgrades according to the specified schedule, PSA was entitled to ask the court for a moratorium on all new sewer connections in the city.

III. Results

Bremerton's record of compliance with the consent decree showed repeated violations that required action by PSA. In 1996, after Bremerton consistently violated the baseline data for several outfalls, PSA notified Bremerton that it would seek to impose the moratorium on all new sewer connections. Subsequent mediation failed and in 1998, PSA filed a motion in Federal court to enforce the moratorium.

In December of 1998, the Court ordered that, in order to avoid a moratorium, Bremerton must agree to a revised construction schedule that accelerated the CSO reduction plan. The court ordered Bremerton and the PSA to enter mediation for the purpose of agreeing to a revision of the plan. In October 2000, PSA and Bremerton entered in to an amended consent decree embodying their agreement regarding the revised construction schedule. Bremerton will complete all remaining CSO projects by December 31, 2007, and must comply with all monitoring and reporting requirements contained in the consent decree.

Oil Refineries

Tesoro Northwest's Anacortes Refinery (1998)

I. Background

Tesoro Northwest operated a refinery in Anacortes under a NPDES permit that contained technology based effluent limitations set by the Washington State Department of Ecology (DOE). In setting these technology based effluent limits, the DOE had relied solely on EPA regulations that were more than ten years old. DOE's technology based limits did not consider the fact that the refinery had achieved a level of pollutant discharge that was 80% lower than allowable pollutant discharge limits in DOE's permit. Also, DOE did not conduct an analysis for dioxins and did not include effluent limits for dioxins in Tesoro's permit. Dioxin analysis was not conducted despite the fact that in 1990 the Environmental Protection Agency (EPA) had first detected dioxins in oil refinery wastewater, and in 1997 the agency had adopted regulations for dioxin analysis before the issuance of a NPDES permit. Additionally, while docked at the facility, oceangoing vessels discharged ballast water that was not subject to Tesoro's NPDES permit.

The plant's operation presented several issues. First, the DOE only required Tesoro to sample for dioxins several years in the future, regardless of EPA evidence that dioxins were currently present in wastewater from other oil refineries. Second, the discharge of a vessel's ballast water was known to cause the introduction of non-native species into marine environments. For example, the green crab and zebra mussel could be introduced to Puget Sound and devastate the native shellfish population. Finally, in setting technology based limits in Tesoro's permit, DOE did not consider Tesoro's prior levels of pollutant discharge that were significantly below EPA's recommended levels. Changing this DOE practice was particularly desirable in light of the fact that Tesoro's permit was the first of five oil refinery permits that were up for renewal in the near future.

II. Legal Action

In 1998, Puget Soundkeeper Alliance joined in a coalition of environmental organizations to challenge DOE's renewal of a Tesoro's NPDES permit. The legal challenge raised three major issues: (1) should the DOE be required, as part of the permitting process, to conduct sampling for dioxins, and consider effluent limits for dioxin; (2) should the discharge of a vessel's ballast water while at the refinery be subject to a NPDES permit; and (3) should the DOE also consider the refinery's past performance as well as EPA regulations when setting effluent limits for the refinery's wastewater?

III. Results

(1) Dioxin - The Pollution Control Hearings Board (PCHB) found that, under the law, DOE was required to conduct testing for dioxin, and consider the possible adverse health effects of dioxin in Tesoro's effluent discharge as part of the permit review process. Therefore, the court ordered DOE to sample Tesoro's effluent for dioxins, conduct an evaluation on the possible health effects of any dioxin found, and include effluent imitations for dioxin if limits are considered necessary.

(2) Ballast water - The PCHB found in Tesoro's favor on this issue and did not require a NPDES permit for ballast water discharge. Presumably, the PCHB was influenced by Tesoro's argument that other maritime law, such as Coast Guard rules, provided sufficient regulation of ballast water discharge.

(3) DOE permitting - This issue remains under appeal to the PCHB.


Unocal Tacoma (1996)

I. Background

From an examination of Unocal's Daily Monitoring Reports (DMRs) submitted to the Washington State Department of Ecology (DOE), Puget Soundkeeper Alliance (PSA) found numerous and excessive violations of permit requirements related to Unocal's petroleum storage, blending, and distribution facility in Tacoma. Unocal had not fully complied with monitoring requirements and had never included monthly average limits, as required in the permit, since the permit had been issued. Unocal had not adopted a stormwater pollution prevention plan or spill control plan as required by the permit. Largely through spills and its stormwater discharge system, Unocal was also violating effluent limits contained in the permit. Violations of effluent limits included the following pollutants and amounts:

(1) Benzene - 7 total violations, 2 violations over ten times the allowable limits and 1 violation almost twenty times the allowable limits.
(2) Copper - 5 total violations, 3 violations over three times the allowable limits.
(3) Zinc - 9 total violations, 4 violations over double the allowable limits.
(4) Petroleum Hydrocarbons - 4 violations, all over double the allowable limits with one violation at thirteen times the allowable limits.

II. Legal Action

From these findings, PSA filed a Notice of Intent to File Suit in February 1996. Negotiation with Unocal resulted in a binding Consent Decree signed in May 1996. The agreement included the following obligations on the part of Unocal:

(1) Compliance with the NPDES permit requirements;
(2) Payment of a $1,000 civil penalty;
(3) Payment of $16,500 to Citizens for a Healthy Bay; and
(4) A new stormwater treatment system equal or superior to the old system.

III. Results

Unocal adopted both a stormwater pollution prevention plan and a spill control plan as required by the permit. Review of DMRs by PSA found 33 continuing violations in 1995. With continuing input from PSA, Unocal implemented construction of a new wastewater treatment system in 1997.

Shipyard Operators

Todd Shipyard (2002)

I. Background

Todd Shipyard operates on Harbor Island, and discharges stormwater in to Elliott Bay and the Duwamish River under a NPDES permit issued by the Washington State Department of Ecology (DOE). Todd exceeded effluent limitations in its stormwater permit for turbidity, total suspended solids, and oil & grease. Todd also failed to comply with compliance schedule requirements in its permit, as well as best management practices and noncompliance notification requirements.
In issuing a draft renewal permit in 2002, DOE did not include final effluent limitations for Todd's stormwater discharges of copper and zinc, and created what amounted to a schedule allowing noncompliance.

II. Legal Action

In February 2002, PSA sent Todd Shipyards a Notice of Intent to File Suit, and filed suit in federal court in April 2002. Settlement negotiations are ongoing. In June 2002, PSA filed comments on the draft NPDES permit, and filed an appeal of Todd's permit.


Marine Industries Northwest's Tacoma Shipyard (1996)

I. Background

Marine Industries Northwest (MINW) operated a Tacoma shipyard with unpaved facilities and no existing storm water treatment system. A NPDES permit, issued to MINW, allowed the discharge of storm water but contained effluent limitations for the discharge of copper, lead, zinc, and Total Suspended Solids (TSS). In addition, the permit included monthly monitoring requirements for these pollutants. For a period of three years prior to December 1995, MINW chronically violated the effluent limits for each of the named pollutants. In addition, the reporting requirements contained in the permit were not followed. For example, in 1995, MINW conducted sampling and reporting only twice for the year, as opposed to the monthly requirements included in the permit.

In December 1995, the Washington State Department of Ecology's (DOE) response to these violations was to propose a modification to the NPDES permit that would suspend the effluent limits and would require MINW to complete an All Known, Available, and Reasonable Methods of Treatment (AKART) Report by the end of an 18-month period. Therefore, for this 18-month period, MINW would not be subject to effluent limits nor would it be subject to any binding requirements for stormwater treatment upgrades to its facility. The DOE took this action despite Commencement Bay's failure to meet state water quality standards and the presence of a multi-million dollar cleanup effort underway for the water body.

II. Legal Action

In January 1996, Puget Soundkeeper Alliance (PSA) appealed the permit modification to the Pollution Control and Hearings Board (PCHB). Most significantly, PSA was concerned with the DOE proposal to completely suspend the NPDES permit effluent limitations. This aspect of DOE's proposal would violate the "anti-backsliding" provision of the Clean Water Act (CWA). In addition, this proposal would set a dangerous precedent for all future permit modifications by the DOE. In addition to the appeal of the permit modifications, PSA formally filed suit against MINW in April 1996, alleging CWA violations.

In June 1996, PSA and MINW reached a settlement agreement that addressed PSA's primary concerns. Under the settlement agreement, MINW would undertake an AKART study that would be followed by the construction of major upgrades to the facility according to a specified schedule. Any failure on the part of MINW to meet scheduled completion dates would subject MINW to a $5,000 per day fine. Also, under the agreement, DOE would address the anti-backsliding violations by formally reinstating the effluent requirements. This aspect of the settlement would prevent DOE's proposed suspension of the effluent limits from being used as a precedent by future permittees.

III. Results

In January 1997, DOE certified the completion of all phases of the facility upgrades. These upgrades included the paving of a portion of the site, the installation of a storm water collection system, and the construction of a water quality and disposal system.


Duwamish Shipyard (1995)

I. Background

Duwamish Shipyard (the Shipyard) was operating under a NPDES permit issued by the Washington State Department of Ecology (DOE) for the discharge of wastewater into Puget Sound. The permit included turbidity limitations and daily maximum discharge limits of Total Suspended Solids (TSS). From investigation of Daily Monitoring Reports (DMRs) submitted to DOE, Puget Soundkeeper Alliance (PSA) identified 35 violations of turbidity limits and 20 violations of the daily maximum TSS from stormwater outfalls. The Shipyard had also violated monitoring requirements in 38 separate instances.

II. Legal Action

From the evidence acquired, PSA filed a Notice of Intent to File Suit in August 1995. In October 1995, PSA and the Shipyard entered into a binding settlement agreement that included the following major elements:

(2) Fully comply with monitoring requirements and fully comply with effluent limits by April 1, 1996, or face the imposition of monetary penalties.
(3) Repair graving dock and prevent recirculating river water contamination.
(4) Implement a facility wide pollution prevention plan.
(5) Provide PSA with all copies of DOE correspondence.
(6) Pay $15,000 to the Green-Duwamish Watershed Alliance.

III. Results

The Shipyard substantially complied with the settlement agreement. Graving dock repairs were completed and there were no further effluent limit violations from recirculating river water. A pollution prevention plan was implemented and the full payment of $15,000 had been received by the Watershed Alliance. Although some were submitted late, the DOE eventually received all DMRs. The Shipyard experienced violations of effluent limits for oil and grease, but provided proof of payment of the monetary penalties for these violations.


Ballard Marine (1994)

I. Background

Puget Soundkeeper Alliance (PSA) volunteer kayakers witnessed activity at Ballard Marine that aroused suspicion. Waste material from the scraping, hydroblasting, and painting of boat hulls was discharged directly into the Ship Canal. The kayakers took photographs of the activity that led to further investigation by PSA.

II. Legal Action and Results

PSA determined that the shipyard was operating without a required permit and filed a Notice of Intent to File in November 1994. In March 1995, PSA and Ballard Marine entered into a binding settlement agreement. Ballard Marine agreed to cooperate with the Washington State Department of Ecology (DOE) for the issuance of a discharge permit. Ballard Marine also agreed to implement a facility wide pollution prevention plan, and to install a treatment system for wastewater discharge. Continued monitoring by PSA confirmed full compliance with the terms of the settlement agreement.


Puget Sound Naval Shipyard (1992)

I. Background

The United States Environmental Protection Agency (EPA) had issued a NPDES permit to the Puget Sound Naval Shipyard (PSNS) in 1986. That permit authorized the discharge of limited amounts of pollutants into the Dyes and Sinclair Inlets, which form part of Puget Sound. Additionally, the permit required PSNS to install and use monitoring equipment, sample effluent, and report on a regular basis to the EPA.

Investigation by the Puget Soundkeeper Alliance (PSA) found violations of the NPDES permit requirements. From a review of the Daily Monitoring Reports (DMRs) submitted to the EPA, PSA found numerous violations by PSNS of effluent limitations for pollutants. For example, in the period from September 1988 through May 1992, PSA found 840 days of violation of the numerical discharge limits. The pollutants discharged included zinc, oil and grease, and various particulates.

PSA obtained further evidence of spills and other unpermitted discharges into Puget Sound. The materials discharged included PCB-contaminated oil, hydrocarbons, chromium, detergent, paint, untreated sewage, battery acid, dissolved metals (including nickel, copper, and zinc), and other miscellaneous pollutants. For instance, in 1990 over 850,000 gallons of untreated sewage were released into Puget Sound through unpermitted spills. Pollutants were also being discharged through seventy-five stormwater discharge points not included in the permit, and a periodically leaking sewer line.

In addition, under the 1986 NPDES permit, PSNS was required to complete and implement a Best Management Practices (BMP) plan. This plan would serve to prevent and minimize the generation and release of pollutants to waters of the United States. As of 1992, PSNS had failed to complete and implement a BMP plan.

II. Legal Action

From the evidence acquired, PSA filed suit under the Clean Water Act in November 1992. Through negotiations with PSNS, the PSA arrived at a binding consent decree in December 1994. Puget Sound Naval Shipyard's primary obligations under the consent decree were as follows:

(1) Maintain substantial compliance with the NPDES limits for discharge of oil and grease at three problematic outfalls. Substantial compliance was defined as no more than two violations per year of any numerical limit.
(2) Complete repairs to the leaking sewer line and further renovations to the entire sewer system leading from the piers and dry-docks by September 30, 1996. Provide PSA with biannual reports on these repairs and renovations.
(3) Monitor pollutant discharge from stormwater discharges.
(4) Complete a BMP and train all personnel in its use within two years.
(5) Provide PSA with copies of all DMRs, spill notifications, and regulatory inspections sent to EPA.
(6) Reimburse PSA for the costs of litigation.

III. Results

In January 1997, PSA sent PSNS a letter acknowledging the completion of two years of monitoring and summarizing PSA's final review of PSNS's water quality improvements. The final review found that PSNS had maintained substantial compliance with oil and grease limits per the consent decree. All sewer line repairs, including additional voluntary upgrades, were completed five months ahead of schedule. Stormwater discharge monitoring had improved substantially, but did not fully meet the requirements of the consent decree and would continue to be monitored by PSA. PSA found that, subsequent to the adoption of a BMP plan, both the frequency and amount of spills had declined dramatically. For example, PSNS reduced the overall number of spills by 60%.

Other Violators

Spadoni Brothers (2002)

I. Background

Spadoni Brothers operated a mining pit facility at Pine Hill, near Port Orchard. Spadoni's NPDES stormwater permit contained monitoring and reporting requirements, and Spadoni failed to comply with these requirements. Spadoni also failed to comply with noncompliance notification and records retention requirements.

II. Legal Action

Based on information from Department of Ecology files on the Pine Hill facility, PSA sent Spadoni Brothers a Notice of Intent to Sue in February 2002. After months of negotiations, PSA and Spadoni Brothers entered in to a settlement agreement in September 2002.

III. Results

As part of the settlement agreement, Spadoni Brothers contributed $5,000 to Citizens for a Healthy Bay to help fund the "Graffiti Gig Harbor Green" stormwater drain stenciling project. As of November 2002, Spadoni Brothers stopped mining activity at the Pine Hill facility.


JA Jack & Sons (2002)

I. Background

JA Jack & Sons operates a limestone processing facility under an NPDES permit, discharging in to the King County storm sewer system and the Duwamish River. Stormwater discharges from the facility violated the NPDES permit limits for turbidity, and JA Jack & Sons failed to comply with monitoring requirements in the permit. The stormwater pollution prevention plan (SWPPP) prepared by JA Jack & Sons under the permit was inadequate.

II. Legal Action

Based on information from Department of Ecology records, PSA sent JA Jack & Sons a Notice of Intent to Sue under the Clean Water Act in February 2002, and filed suit in federal court in April 2002.

III. Results

Ongoing settlement negotiations.


Georgia Pacific Corporation's Bellingham Pulp Mill (1997)

I. Background

Georgia Pacific Corporation had operated a pulp mill in Bellingham since 1963. This mill produced bleached pulp that was sold as market pulp and processed into tissue paper. Additionally Georgia Pacific manufactured chlorine at the site, using the mercury cell process. While some of the chlorine was used on-site in the bleaching process, the majority was shipped by rail off-site.

In January 1996, the Washington State Department of Ecology (DOE) issued an order to Georgia Pacific in an attempt to address excessive mercury discharges by the company in violation of its NPDES permit. The order directed Georgia Pacific to conduct a thorough study of its mercury sampling apparatus and evaluate all potentially feasible source control alternatives. Results of the study were required to be submitted to the DOE within ninety days. Georgia Pacific never fully complied with this order.

II. Legal Action

Puget Soundkeeper Alliance (PSA) obtained evidence of the highly elevated levels of mercury being discharged into Puget Sound in violation of the Clean Water Act. In July 1997 PSA filed a Notice of Intent to File Suit. PSA alleged a history of non-compliance with effluent limits and reporting requirements contained in Georgia Pacific's NPDES permit. Specifically, PSA alleged 28 separate violations of both the daily maximum and monthly average limits for discharge of mercury from 1995 to 1998.

These alleged violations included two months where the monthly average was more than eight times the allowable limit and one month where the monthly average exceeded the allowable limits for mercury by a factor of twenty. Georgia Pacific Corporation allegedly had also failed to fully comply with mercury discharge monitoring requirements contained in its NPDES permit for the preceding three years.

PSA formally filed a complaint in the matter in November 1997. PSA and Georgia Pacific reached a settlement agreement in October 1998. The agreement required Georgia Pacific to fully comply with the January 1996 DOE order. Additionally, Georgia Pacific would pay a lump sum of $55,000 to PSA to fund environmental improvement projects and settle attorney's fees.

III. Results

The settlement agreement was subsequently amended in August 1999. Under the revised agreement, Georgia Pacific would not be required to complete the study of mercury in exchange for an additional payment by Georgia Pacific of $5,000 and written confirmation of Georgia Pacific's intent to close the chlorine manufacturing plant by December 31, 1999. Georgia Pacific then closed the chlorine manufacturing facility.


Warm Beach Christian Camp and Conference Center (2000)

I. Background

PSA filed a Notice of Intent to Sue in April 2000 for violations of its NPDES permit including exceeding effluent limitations for BOD and TSS and monitoring and reporting requirements.

II. Legal Action

A Notice of Intent to Sue was delivered to Warm Beach in April 2000. A settlement agreement was completed in September 2000.

III. Results

The settlement agreement included compliance with effluent limitations by June 1, 2001 and TSS and BOD by August 1, 2002. The settlement also included WBCC hosting a Spartina workshop, local septic system workshop and the donation of conference facilities for two three-day environmental conferences. WBCC built a secondary treatment facility that was completed in 2003.


Warm Beach Christian Campground in Stanwood (1994)

I. Background

Warm Beach Christian Campground (WBCC) discharged wastewater under a NPDES permit that included effluent limits on Biological Oxygen Demand (BOD), Total Suspended Solids (TSS), and Fecal Coliform (FC). From an analysis of Daily Monitoring Reports (DMRs) submitted to the Washington State Department of Ecology (DOE), Puget Soundkeeper Alliance (PSA) identified numerous violations of the effluent limits and reporting requirements included in the NPDES since January 1990. Specifically, WBCC committed 116 violations of monthly and weekly maximum averages for the discharge of BOD, TSS, and FC. In addition, PSA identified 27 instances of late or missing DMRs required to be submitted to the DOE.

II. Legal Action

In October 1994, PSA filed suit against WBCC under the citizen suit provision of the Clean Water Act seeking an injunction against further violations and civil penalties. PSA and WBCC arrived at a settlement agreement in July 1995. WBCC agreed to undertake significant upgrades to its sewage treatment lagoon including rehabilitation of the lagoon dike, installation of a lagoon baffle, and the construction of fencing around the lagoon. In addition, WBCC agreed to pay monetary penalties for each ongoing violation, and contribute $5,000 to the Stillaguamish/Snohomish Fisheries Enhancement Task Force (Fisheries Enhancement). Under the agreement, WBCC would comply with discharge monitoring requirements and provide copies to PSA.

III. Results

Subsequent to the settlement agreement, PSA continued to monitor WBCC's compliance. WBCC provided proof of payment of $5,000 to Fisheries Enhancement. All lagoon upgrades had been fully completed and documented by January 1996. In addition, WBCC had complied fully with all DMR reporting requirements.


Cadman Cement in Seattle (1994)

I. Background

From examination of Washington State Department of Ecology (DOE) records, Puget Soundkeeper Alliance (PSA) obtained evidence that Cadman Cement was discharging stormwater in violation of its NPDES permit. PSA identified 154 violations of turbidity limits in excess of 100%, violations of Total Suspended Solids (TSS) limits, and 31 instances of late or missing reports.

II. Legal Action

From the evidence acquired, PSA filed a Notice of Intent to File Suit in June 1994.
PSA and Cadman Cement arrived at a binding consent decree in May 1995. The agreement obligated Cadman Cement to pay a $1,500 civil penalty, pay $28,500 to local environmental organizations, and spend $100,000 on environmental improvements at the facility. Additionally, Cadman would implement technology improvements specified in their NPDES permit.

III. Results

Monitoring by PSA confirmed the payment of $1,500 as a civil penalty and the contribution of $28,500 to local environmental organizations. Cadman also provided PSA with confirmation of a $100,000 expenditure to upgrade the facility, as well as plans to spend an additional $240,000 for further improvements. Although Cadman did experience a period of further violations, by 1997 the company had fully implemented a stormwater retention and recycling program that largely eliminated discharges.

State Agency

Department of Ecology (2001)

I. Background

The Washington State Department of Ecology (DOE) reissued two general NPDES permits for municipal and industrial stormwater discharges. These are major permitting actions, as these two permits authorize stormwater discharges from over 2,000 facilities and sites across Washington. The permits were reissued virtually without change from the last version, prepared in 1995.

The two permits do no adequately protect water quality. Neither specifically prohibits discharges that cause or contribute to violations of water quality standards, as both the Clean Water Act and state pollution laws require. The permits fail to include, among other factors: numeric effluent limitations or effluent sampling and analysis requirements, effective monitoring requirements, significant compliance schedules, mandatory application of AKART (all known, available, and reasonable methods of pollution control).

Challenging these permits is important because DOE must hold the many facilities the permits regulate to adequate and enforceable pollution control standards to minimize deleterious environmental impacts. Stormwater discharges are widely recognized as major contributors to water quality degradation in Washington.

II. Legal Action

After submitting comments on the permits' deficiencies to DOE, a coalition of environmental groups (Puget Soundkeeper Alliance, Resources for Sustainable Communities, Waste Action Project, Washington Public Employees for Environmental Responsibility, and Citizens for a Healthy Bay) appealed these two permits to the Pollution Control Hearings Board (PCHB).

III. Results

Ongoing.

 

[HOME]
Puget Soundkeeper Alliance
5309 Shilshole Ave NW

Suite 215
Seattle, WA 98107
(206) 297-7002

Puget Soundkeeper Alliance Homepage